|
| | Irrigation Pond Permit Application
Process
The following guidance is offered
for those persons considering developing an irrigation pond or
impoundment. Typically, permits are required both from the Army
Corps of Engineers (COE) and from either the Maine Department of
Environmental Protection (DEP) or the Land Use Regulation
Commission (LURC). Assistance with the irrigation water
management plan may be available from the USDA Natural Resources
Conservation Service (NRCS) and/or the local Soil and Water
Conservation District (SWCD), subject to local priorities and workloads.
Permit applicants are required to
demonstrate that all reasonable alternatives to impacting
wetlands are considered. The guiding principals are Avoid,
Minimize, and Mitigate.
STEP 1: Develop a whole farm
irrigation water management plan. Include in the plan a detailed
analysis of alternative water sources or sites. (Possible NRCS assistance)
The irrigation management
plan is the master plan for water use. Typically, this
includes the total number of acres to be irrigated, the
amount of water needed, the potential sources of water,
and a description of the water management practices that
will be used to minimize water usage.
Very Important: Include
in the plan a description and analysis of all reasonable
alternatives. Alternatives might include sites with less
wetland impacts, wells, impoundments on upland sites, or
withdrawals form existing surface waters.
STEP 2: Applicant will
review the permit application requirements for both the state and
federal regulatory agencies.
STEP 3. Applicant will
request a pre-application site visit by all of the responsible
state and federal agencies.
A site visit is advisable
in order that the permitting and review agencies (state
and federal) may review the irrigation farm plan, view
and discuss the alternative water sources and raise
questions that may need to be addressed in the permit
application. Mitigation requirements can be introduced
here but will likely be determined only after the full
permit application is received.
STEP 4. Applicant will
complete and submit the permit application (include wetland
delineation).
Choose the applicable
state permit application form (LURC form for unorganized
territories and the DEP application for organized
townships). The COE will accept either one of these forms
for the federal permit application.
It is important to work
with both the state and federal permitting agencies
through the entire process. The completed application can
be submitted simultaneously to both the COE and the
state. However, there may be some advantages to
submitting to the COE first then to LURC or DEP after the
COE permit is granted. This is because both state
agencies require completed drawings by a professional
engineer at the time of application. The COE requires
completed engineering drawings only as a condition of a
granted permit.
STEP 5. Applicant will
complete USDA Swampbuster requirements for a wetland exemption.
In order to maintain USDA
program benefits, an exemption and plan for manipulating
wetlands for non-agricultural purposes (CWNA) must be
granted by NRCS. This is initiated by completing form
AD-1026 at a FSA office.
< Back to Irrigation Pond
Information...
| |
|