Irrigation Pond Permit Application
Process
The following guidance is offered for those persons considering developing an
irrigation pond or impoundment. Typically, permits are required both from the
Army Corps of Engineers (COE) and from either the Maine Department of
Environmental Protection (DEP) or the Land Use Regulation Commission (LURC).
Assistance with the irrigation water management plan may be available from the
USDA Natural Resources Conservation Service (NRCS) and/or the local Soil and
Water Conservation District (SWCD), subject to local priorities and workloads.
Permit applicants are required to demonstrate that all reasonable alternatives
to impacting wetlands are considered. The guiding principals are Avoid,
Minimize, and Mitigate.
STEP 1: Develop a whole farm irrigation water management plan. Include in the
plan a detailed analysis of alternative water sources or sites. (Possible NRCS
assistance)
The irrigation management plan is the master plan for water use.
Typically, this includes the total number of acres to be irrigated, the
amount of water needed, the potential sources of water, and a description of
the water management practices that will be used to minimize water usage.
Very Important: Include in the plan a description and analysis of
all reasonable alternatives. Alternatives might include sites with less
wetland impacts, wells, impoundments on upland sites, or withdrawals form
existing surface waters.
STEP 2: Applicant will review the permit application requirements for both
the state and federal regulatory agencies.
STEP 3. Applicant will request a pre-application site visit by all of the
responsible state and federal agencies.
A site visit is advisable in order that the permitting and review
agencies (state and federal) may review the irrigation farm plan, view and
discuss the alternative water sources and raise questions that may need to
be addressed in the permit application. Mitigation requirements can be
introduced here but will likely be determined only after the full permit
application is received.
STEP 4. Applicant will complete and submit the permit application (include
wetland delineation).
Choose the applicable state permit application form (LURC form for
unorganized territories and the DEP application for organized townships).
The COE will accept either one of these forms for the federal permit
application.
It is important to work with both the state and federal permitting
agencies through the entire process. The completed application can be
submitted simultaneously to both the COE and the state. However, there may
be some advantages to submitting to the COE first then to LURC or DEP after
the COE permit is granted. This is because both state agencies require
completed drawings by a professional engineer at the time of application.
The COE requires completed engineering drawings only as a condition of a
granted permit.
STEP 5. Applicant will complete USDA Swampbuster requirements for a
wetland exemption.
In order to maintain USDA program benefits, a determination must be made
that any wetland manipulation (Food Security Act label: Manipulated Wetland
WX) will not make possible the production of an agricultural commodity. This
is initiated by completing form AD-1026 at a FSA office.
< Back to Irrigation Pond
Information...
|